UNOPS 6th QRM PPT - ZEAT-BEAD

Feeder Roads Construction in Support of Trade and Market Development in Greater Bahr el Ghazal Region

Million Ali Abate. UNOPS, April 2016

Construction of approximately 120km of Feeder Roads. Feasibility Study & road segment selection. Engineering Design using South Sudan Low Volume Road Design Manual and National Feeder Roads Requiremen. Procurement of Contractors. Implementation. Improved Stakeholder Capacity. Capacity development of the State Ministries of Physical Infrastructure, local contractors and communities. Community sensitization and labour intensive support activities. Develop Sustainable Road Maintenance Concept Note.

Lot 1: (Kangi Bar Urud- 31 km)

Lot 2: (Achol Pagong to Ayein Market- 27 km)

Lot 3: (Gok Machar to Mayom Angok- 35 km)

UNOPS is working with UNIDO and GIZ in identifying support required for market infrastructure facilities at selected market areas along the Feeder Roads. UNOPS is working with SORUDEV partners in relation to community sensitization, mobilization and capacity building activities.

Just recruited Monitoring and Evaluation Expert who will be exclusively engaged on the evaluation and monitoring aspect of the anticipated results/outcomes and objectively verifiable indicators of achievement. Currently, the M&E expert is preparing M&E framework, PMEP, indicators assessment tools and the like.

New State officials need to be incorporated and appraised of the progress made and commitments of the previous office holders. New strategy on the resettlement action plan required for future projects. Maintaining strong synergy among key stakeholders requires regular communication, consultation and information sharing.