MTR classification | Action number | Title | Decision: TEN-T funding € | Proposed: TEN-T funding € | Reduction |
1) Cancellation (partial or complete) | 2007-CZ-22090-S | Praha-Beroun, New Railway Connection - Implementation of a detailed geotechnical survey and development of a Construction Project | 14.500.000 | 0 | 14.500.000 |
| 2007-CZ-60020-P | ERTMS deployment on corridor E (Dresden-Budapest) Onboard Equipment of Ceské dráhy, a.s. | 1.000.000 | 0 | 1.000.000 |
| 2007-DE-60080-P | Ausrüstung der Eisenbahnstrecke von Aachen West (Grenze) bis Oberhausen mit ETCS als Teil des Korridors F Aachen ¿ Warschau | 9.000.000 | 0 | 9.000.000 |
| 2007-EU-24090-S | Iron Rhine | 7.285.000 | 2.833.519 | 4.451.481 |
2) Completed by end 2013 | 2007-AT-01130-P | Works for construction of new high speed line between Kundl/Radfeld and Baumkirchen | 58.300.000 | 58.300.000 | 0 |
| 2007-AT-17170-P | Works for upgrading of the cross-border section Salzburg- German border | 37.880.000 | 37.880.000 | 0 |
| 2007-AT-60450-P | ERTMS deployment on Corridor B (Stockholm-Naples) ¿ Austrian section | 12.000.000 | 12.000.000 | 0 |
| 2007-CZ-23020-S | Modernisation of the Blazovice - Nezamyslice line section | 7.070.000 | 7.070.000 | 0 |
| 2007-CZ-60010-P | Corridor E: ERTMS trackside equipment in the Czech Republic | 20.780.000 | 20.780.000 | 0 |
| 2007-DE-01050-P | Verkehrsprojekt Deutsche Einheit (VDE) 8.2, Neubaustrecke (NBS) Erfurt - Leipzig/Halle, Abschnitt Erfurt- Halle bzw. Gröbers | 57.000.000 | 57.000.000 | 0 |
| 2007-DE-02020-P | Aachen - Köln | 14.780.000 | 11.854.400 | 2.925.600 |
| 2007-DE-17010-P | Neubaustrecke Wendlingen - Ulm | 101.450.000 | 101.450.000 | 0 |
| 2007-DE-18030-P | Neubau der Eisenbahnbrücke über die Donau bei Deggendorf | 7.010.000 | 7.010.000 | 0 |
| 2007-DE-18050-S | Variantenunabhängige Untersuchungen zum Ausbau der Donau zwischen Straubing und Vilshofen | 16.500.000 | 16.500.000 | 0 |
| 2007-DE-60490-P | Ausrüstung von Lokomotiven der Railion Deutschland AG | 4.800.000 | 3.200.000 | 1.600.000 |
| 2007-DK-20060-S | Studies for the capacity improvements of the section between Copenhagen and Ringsted | 10.990.000 | 10.990.000 | 0 |
| 2007-DK-20070-S | Studies for upgrading the railway access lines to the future Fehmarn Belt fixed link - from Ringsted to Rødby and the intersection in Kastrup | 11.700.000 | 11.700.000 | 0 |
| 2007-EE-27010-S | Studies for a European gauge line for Rail Baltica (Estonian section) | 1.000.000 | 1.000.000 | 0 |
| 2007-EE-27020-P | Cross-border section Tartu - Valga railway reconstruction/upgrading | 10.750.000 | 10.750.000 | 0 |
| 2007-EL-07020-S | Studies for the upgrading of sections on the Vertical Axis Thessaloniki - Serres - Promachonas | 2.350.000 | 2.350.000 | 0 |
| 2007-EL-07040-S | Studies for the development of the Motorway-project of PP7 (Igoumenitsa/Patras-Athens-Sofia-Budapest Motorway Axis) | 1.125.000 | 1.125.000 | 0 |
| 2007-ES-03070-P | CONEXIÓN ESPAÑA - FRANCIA POR LA FACHADA ATLÁNTICA. LÍNEA DE ALTA VELOCIDAD MADRID - PAIS VASCO - FRONTERA FRANCESA. TRAMOS VALLADOLID - BURGOS - VITORIA. OBRAS DE PLATAFORMA VALLADOLID - BURGOS | 24.999.972 | 24.999.972 | 0 |
| 2007-ES-03140-S | ESTUDIOS PARA LA CONSTRUCCION DE LA LÍNEA DE ALTA VELOCIDAD MADRID - PAIS VASCO - FRONTERA FRANCESA. TRAMOS VALLADOLID - BURGOS - VITORIA. | 14.650.000 | 14.650.000 | 0 |
| 2007-ES-03150-P | LÍNEA DE ALTA VELOCIDAD MADRID ¿ PAIS VASCO ¿ FRONTERA FRANCESA. OBRAS DE PLATAFORMA DE LOS TRAMOS ARRAZUA/MONDRAGON | 26.759.986 | 26.759.986 | 0 |
| 2007-ES-19060-P | Obras en la Conexión ferroviaria Corredor Mediterráneo ¿ Línea de alta velocidad Madrid-Barcelona-Frontera Francesa | 22.860.000 | 22.860.000 | 0 |
| 2007-EU-03080-P | Studies and Works for the High-Speed Railway Axis of South-West Europe (PP3) - Lisbon-Madrid Axis: Cross-Border Section Evora-Merida | 312.660.000 | 312.660.000 | 0 |
| 2007-EU-03110-P | Works for construction of a high-speed railway section between Perpignan and Figueres | 69.750.000 | 69.750.000 | 0 |
| 2007-EU-60040-P | EEIG ERTMS Users Group ¿ testing activities | 6.000.000 | 6.000.000 | 0 |
| 2007-EU-60120-P | ERTMS Implementation on the Railway Corridor D (Valencia - Budapest) | 21.040.000 | 21.040.000 | 0 |
| 2007-EU-60410-S | Programme Management Office (PMO) for the ERTMS deployment on the corridor from Rotterdam to Genoa | 1.130.000 | 1.130.000 | 0 |
| 2007-EU-60440-P | Mise en place de l'ERTMS sur les rames THALYS | 4.800.000 | 4.800.000 | 0 |
| 2007-FI-12010-P | Rail connection from Kouvola to Kotka/Hamina ports, works for improving and costruction of a new railway yard | 6.600.000 | 6.600.000 | 0 |
| 2007-FI-12040-P | Main railway connection to Russian border , works for development of railway section between Lahti and Vainikkala | 23.150.000 | 23.150.000 | 0 |
| 2007-FR-03130-S | Etudes préliminaires et d'APS en vue de la construction d'une nouvelle ligne ferroviaire entre Bordeaux et la Frontière Espagnole | 17.100.000 | 17.100.000 | 0 |
| 2007-FR-17210-P | Ligne à grande vitesse (LGV) Est Européenne - Seconde phase, section Baudrecourt- Vendenheim (Etudes et travaux préparatoires) | 18.000.000 | 18.000.000 | 0 |
| 2007-FR-24070-P | Ligne à grande vitesse (LGV) Rhin - Rhône Branche Est | 198.000.000 | 198.000.000 | 0 |
| 2007-HU-06100-S | Studies for preparation of approval of the railway line section Budapest - Keleti - Miskolc - Nyiregyhaza | 8.000.000 | 8.000.000 | 0 |
| 2007-HU-18090-S | Studies for Improvement of the navigability on the Danube (Hungarian section of the Priority Project No. 18) | 4.000.000 | 4.000.000 | 0 |
| 2007-HU-22020-S | Preparation of design for approval for the railway line section Biatorbagy (incl.) - Tata (excl.) of PRIORITY AXIS NO. 22 | 1.250.000 | 1.250.000 | 0 |
| 2007-IE-26010-S | Dublin Interconnector Tunnel Study- Design and Railway Order Phase | 10.000.000 | 10.000.000 | 0 |
| 2007-IT-06020-S | Tratta Ronchi sud - Trieste: Progetto Prioritario 6 - sezione Nazionale | 24.000.000 | 24.000.000 | 0 |
| 2007-IT-24010-S | Railway node of Genova - Study for upgrading the section Genova Voltri-Genova Brignole | 5.050.000 | 5.050.000 | 0 |
| 2007-IT-60030-P | Migration towards ERTMS/ETCS for Trenitalia on-board equipment | 7.000.000 | 7.000.000 | 0 |
| 2007-LV-27050-S | Studies for a European gauge line (Latvian section) | 1.100.000 | 1.100.000 | 0 |
| 2007-NL-05020-P | Works for replacement of legacy systems by 15/25 kVAC on two remaining sections in the Netherlands of the railway corridor Rotterdam Genoa. | 19.880.000 | 19.880.000 | 0 |
| 2007-NL-18010-P | Maasroute, Upgrade of Inland Waterways from class Va to class Vb specifications | 81.780.000 | 74.749.858 | 7.030.142 |
| 2007-NL-60060-P | ERTMS implementation on the railway corridor Rotterdam Genoa - Netherlands Part - Kijfhoek and Zevenaar | 4.650.000 | 4.650.000 | 0 |
| 2007-NL-60160-P | Serial fitment of onboard ETCS equipment SRS 2.3.0 in 109 freight locomotives. | 9.050.000 | 7.750.000 | 1.300.000 |
| 2007-NL-60310-P | ERTMS implementation the Railway Corridor Rotterdam Genoa Netherlands part - Section Port Railway of Rotterdam | 4.500.000 | 4.500.000 | 0 |
| 2007-NL-60380-P | Retrofit of 90 Siemens ES64F4 E-locomotives with Alstom ETCS L2 equipment for usage on EU freight corridors and various conventional networks | 9.000.000 | 9.000.000 | 0 |
| 2007-SE-12090-P | Works for construction of the road section Norra Länken | 56.150.000 | 56.150.000 | 0 |
| 2007-SE-12100-P | Works for construction of Malmoe - Citytunnel project | 51.830.000 | 51.830.000 | 0 |
3) Conditional extension 2014-2015 | 2007-AT-17040-P | Works and Studies for upgrading the Wien-Bratislava railway line (6 sub-projects) | 129.850.000 | 129.850.000 | 0 |
| 2007-BE-18040-P | Etudes de construction d¿une écluse de 225mX25m (classe VIb) à Huy (Ampsin-Neuville) et construction d¿une écluse de 225mX25m (classe VIb) à Flémalle (Ivoz-Ramet), toutes deux sur la Meuse | 17.590.000 | 17.590.000 | 0 |
| 2007-BE-18070-P | Construction of a 225 x 25 m chamber navigation lock, its ancillary works and a pumping station/ hydroelectric power plant on the Albert Canal, to the east of the existing lock complex at Lanaye. | 26.930.000 | 26.930.000 | 0 |
| 2007-DE-04020-P | Ausbaustrecke 23 (Grenze D/F) Saarbrücken - Ludwigshafen (POS Nord) | 10.000.000 | 10.000.000 | 0 |
| 2007-DE-17020-P | Ausbau des Abschnittes Freilassing-Grenze D/A (Salzburg) des TEN-Korridors Paris - München - Bratislava | 8.544.272 | 8.544.272 | 0 |
| 2007-DE-17200-P | Aus- und Neubaustrecke Stuttgart-Wendlingen einschl. Stuttgart 21 | 114.470.000 | 114.470.000 | 0 |
| 2007-DE-20010-S | Eisenbahn-Hinterlandanbindung zur Fehmarnbeltquerung von Lübeck nach Puttgarden | 12.700.000 | 12.700.000 | 0 |
| 2007-DE-24030-S | Studien für den Bau der Neubaustrecke Rhein/Main-Rhein/Neckar | 35.450.000 | 22.988.760 | 12.461.240 |
| 2007-DE-24040-P | Duisburg - Emmerich | 63.330.000 | 63.330.000 | 0 |
| 2007-DE-24060-P | Ausbaustrecke / Neubaustrecke Karlsruhe - Basel mit teilweisen Ausbaumaßnahmen an der bestehenden Strecke | 94.500.000 | 94.500.000 | 0 |
| 2007-DE-60320-P | Ausrüstung der Eisenbahnstrecke von Emmerich (Grenze) bis Basel (Grenze) mit ETCS als Teil des Korridors A Rotterdam - Genua | 23.250.000 | 23.250.000 | 0 |
| 2007-EL-29010-S | Railway line between Antirrio and Ioannina, studies for designing of the new line Antirrio-Ioannina | 21.500.000 | 21.500.000 | 0 |
| 2007-EL-29030-S | Studies for standardisation and upgrading design for the existing Patras - Pyrgos - Kalamata railway | 15.500.000 | 15.500.000 | 0 |
| 2007-ES-03050-P | Construcción de la Nueva Red Ferroviaria en el Pais Vasco ( Y Vasca) - Tramo Guipuzcoano | 7.119.000 | 7.119.000 | 0 |
| 2007-EU-01180-P | PRIORITY PROJECT TEN NO. 1 BRENNER BASE TUNNEL - WORKS | 592.650.000 | 592.650.000 | 0 |
| 2007-EU-01190-S | PRIORITY PROJECT TEN NO. 1 BRENNER BASE TUNNEL - STUDIES | 193.350.000 | 193.350.000 | 0 |
| 2007-EU-06010-P | Nouvelle liaison ferroviaire Lyon-Turin Partie commune franco-italienne de la section internationale | 671.800.000 | 662.620.000 | 9.180.000 |
| 2007-EU-06030-S | Crossborder Railway Line Trieste/Divaca : study and design of the Trieste-Divaca-Ljubljana-Budapest-Ukrainian Border | 50.700.000 | 50.700.000 | 0 |
| 2007-EU-16010-S | Studies for the construction of the new high capacity line through the Pyreneans | 5.000.000 | 5.000.000 | 0 |
| 2007-EU-19010-P | Studies and Works in the High -Speed Rail Interoperability in Iberian Peninsula (PP19) - Oporto-Vigo Axis:Cross-Border Section Ponte de Lima-Vigo | 244.140.000 | 244.140.000 | 0 |
| 2007-EU-20050-P | Studies and Works for the construction of Fehmarn Belt Fixed Rail-Road link | 338.900.000 | 265.720.000 | 73.180.000 |
| 2007-EU-22070-S | Studies for the development of the Railway Priority Project No. 22 | 6.500.000 | 6.500.000 | 0 |
| 2007-EU-60400-P | Deployment of ERTMS on the corridor Antwerp-Basel/Lyon | 88.980.000 | 88.980.000 | 0 |
| 2007-FI-12050-P | Works for the development of the railway connection between Helsinki airport and the PP12 lines | 17.760.000 | 17.760.000 | 0 |
| 2007-FR-03120-P | Désaturation du noeud ferroviaire de Bordeaux | 21.277.000 | 21.277.000 | 0 |
| 2007-IT-60360-P | Trackside ERTMS equipment on Italian part of Corridor A (600 km) | 33.000.000 | 33.000.000 | 0 |
| 2007-LT-27030-P | 1)Building of new European gauge line on the cross-border section PL border - Marijampole 2) cross-border section Siauliai - LV border. Reconstruction/Upgrading | 72.800.000 | 45.703.339 | 27.096.661 |
| 2007-LT-27040-S | Studies for Rail Baltica, Lithuanian part: a)section PL border - Marijampole in European Gauge; b) Improvement of existing line; c)contribution to global Rail Baltica study for European Gauge | 16.070.000 | 16.070.000 | 0 |
| 2007-PT-03030-P | Studies and Works in the High-Speed Railway Axis of South-West Europe (PP3) - Lisbon-Madrid Axis: Third Tagus Crossing (TTC) | 51.310.000 | 51.310.000 | 0 |
4) Conditional extension & partial cancellation (post 2015) | 2007-AT-18020-P | Implementation of the Integrated River Engineering Project Danube East of Vienna km 1921.0 - 1872.7 | 36.389.769 | 22.420.501 | 13.969.268 |
| 2007-BE-02030-P | Diabolo - Raccordement ferroviaire de l'aéroport de Zaventem au réseau à grande vitesse Thalys | 15.000.000 | 14.920.689 | 79.311 |
| 2007-BE-28050-P | EuroCap-Rail modernisation de l'axe ferroviaire Bruxelles-Luxembourg | 30.180.000 | 21.331.958 | 8.848.042 |
| 2007-DE-17220-P | Ausbaustrecke 23 Kehl - Appenweier (POS Süd) | 26.950.000 | 23.426.931 | 3.523.069 |
| 2007-EU-03040-P | Atlantic branch of the international section of PP3 Vitoria-Dax ( estudios y obras para la nueva linea de alta velocidad) | 70.000.000 | 56.808.784 | 13.191.216 |
| 2007-EU-30010-P | The Seine-Scheldt Inland Waterway Network - Cross-border section between Compiègne and Ghent | 420.190.000 | 375.928.794 | 44.261.206 |
| 2007-FR-03010-P | Contournement de Nîmes et Montpellier (Etudes et travaux) | 56.260.000 | 47.571.056 | 8.688.944 |
| 2007-IT-01030-M | Southern Access line to Brenner | 58.810.000 | 45.920.000 | 12.890.000 |
| 2007-LU-28020-P | EuroCap-Rail. Modernisation de l'axe 3 Bruxelles-Luxembourg-Strasbourg | 27.000.000 | 3.517.839 | 23.482.161 |
| 2007-LV-27060-P | 1)Reconstruction/upgrading: cross-border section north Valmeira - Valka abd cross-border section south Jelgava - LT border. 2) Reconstruction/upgrading Jugla (Riga city border station) - Valmiera | 22.330.000 | 6.541.950 | 15.788.050 |
| 2007-UK-13010-P | Package for improvements and upgrade of road infrastructure on Priority Project 13: Sections of A14, M6 and A1 | 80.710.000 | 77.665.741 | 3.044.259 |
Grand Total | | | 5.300.799.999 | 4.989.309.349 | 311.490.650 |