European Commission Vice President Siim Kallas today published the first ever mid term review of 92 priority Trans-European Networks infrastructure projects, co-financed by the Commission under the TEN-T programme for 2007-2013. The review provides a detailed "snap shot" of the state of play of each major infrastructure project in terms of financing and completion. The aim is to introduce more accountability into the funding process and to make sure that EU money is being well spent. Over half (52.2%) of these 92 major pan-European infrastructure projects are still on track for completion by December 2013, despite the tough financial environment. For the rest, the mid term review applies a strict "use it or lose it" principle. A two year extension is granted to credible projects which are facing difficulties in the economic crisis, to support their completion. But for projects which, at this mid term stage, are no longer credible, EU funding will be cut and re-allocated (see below for lists of projects).
Commission Vice-President Siim Kallas, responsible for transport, said: "This mid term review is about supporting key investments in infrastructure and delivering value for taxpayers' money. I am greatly encouraged that despite the tough economic circumstances, many Member States are making the right decisions to invest in the economic infrastructure that is critical to Europe's recovery. With this review, we want the scarce resources available to be managed strictly. But where projects are no longer meeting their objectives then EU funding must be cut and re-allocated so we make best use of the limited resources."
Main results of the mid term review
The review assesses 92 separate funding decisions worth around three-quarters (5.3 billion Euro) of the EU's 8 billion Euro TEN-T budget (2007-2013).
The review shows that 48 projects out of 92 will be finished by the deadline of 31 December 2013 (52.2%).
A further 29 projects of the projects (31.5%) are credible in terms of structure and financing and could be complete by 2015. For this reason, and faced with an exceptional period of financial crisis, the Commission will give a two year extension for the use of EU funding until 2015. This extension will be subject to specific political, technical and financial conditions, which will optimise the effectiveness of the TEN-T programme. The same budgetary rigour will apply for any future delays of projects; activities that would slip beyond 2015 will be cut.
10 projects (10.9%) have received a conditional extension to 2015 but have had a partial reduction of EU funding imposed.
5 projects are not credible at this stage (5.4%) and for these projects EU funding will be cut and re-allocated.
Moreover, any project in the above four categories has been screened in a detailed way for each of their objectives. In case these objectives are no longer met, the related budget will be cut.
As a result of the above analysis, around €311 million will be liberated to be re-injected into new calls for proposals under the current TEN-T programme.
What are Trans European Networks
The TEN-T programme was established by the European Union to help build missing links and remove transport bottlenecks, creating a single, multimodal network of transport corridors throughout Europe.
Projects are financed by Member States and the European Commission. Up to a maximum of 30% of the budget for infrastructure works on a project and 50% for studies can come from the European TEN-T budget.
The 92 projects reviewed by the Commission correspond to an overall investment of 32.647 billion Euro and a TEN-T (European) contribution of 5.3 billion Euro.
The 92 projects key parts of the 30 priority TEN-T networks /major inter-modal corridors across the EU (see link below for details).
The 30 TEN-T priority networks are major infrastructure projects, often involving several countries, for example: the high-speed railway axis Paris-Bruxelles/Brussel-Köln-Amsterdam-London: PBKAL; or the Railway axis Gdańsk-Warszawa-Brno/Bratislava-Wien.
For a map and complete list of TEN-T 30 priority networks / projects (2007-2010) see below:
http://tentea.ec.europa.eu/en/ten-t_projects/30_priority_projects/
More information:
The list of 92 projects assessed by the TEN-T review is attached.
For more information about TEN-T, visit
http://ec.europa.eu/transport/infrastructure/index_en.htm
For more information about the TEN-T Agency, please visit
http://tentea.ec.europa.eu/en/home.htm
Annex
|
|
| Data |
|
|
MTR classification | Action number | Title | Decision: TEN-T funding € | Proposed: TEN-T funding € | Reduction |
1) Cancellation (partial or complete) | 2007-CZ-22090-S | Praha-Beroun, New Railway Connection - Implementation of a detailed geotechnical survey and development of a Construction Project | 14.500.000 | 0 | 14.500.000 |
| 2007-CZ-60020-P | ERTMS deployment on corridor E (Dresden-Budapest) Onboard Equipment of Ceské dráhy, a.s. | 1.000.000 | 0 | 1.000.000 |
| 2007-DE-60080-P | Ausrüstung der Eisenbahnstrecke von Aachen West (Grenze) bis Oberhausen mit ETCS als Teil des Korridors F Aachen ¿ Warschau | 9.000.000 | 0 | 9.000.000 |
| 2007-EU-24090-S | Iron Rhine | 7.285.000 | 2.833.519 | 4.451.481 |
2) Completed by end 2013 | 2007-AT-01130-P | Works for construction of new high speed line between Kundl/Radfeld and Baumkirchen | 58.300.000 | 58.300.000 | 0 |
| 2007-AT-17170-P | Works for upgrading of the cross-border section Salzburg- German border | 37.880.000 | 37.880.000 | 0 |
| 2007-AT-60450-P | ERTMS deployment on Corridor B (Stockholm-Naples) ¿ Austrian section | 12.000.000 | 12.000.000 | 0 |
| 2007-CZ-23020-S | Modernisation of the Blazovice - Nezamyslice line section | 7.070.000 | 7.070.000 | 0 |
| 2007-CZ-60010-P | Corridor E: ERTMS trackside equipment in the Czech Republic | 20.780.000 | 20.780.000 | 0 |
| 2007-DE-01050-P | Verkehrsprojekt Deutsche Einheit (VDE) 8.2, Neubaustrecke (NBS) Erfurt - Leipzig/Halle, Abschnitt Erfurt- Halle bzw. Gröbers | 57.000.000 | 57.000.000 | 0 |
| 2007-DE-02020-P | Aachen - Köln | 14.780.000 | 11.854.400 | 2.925.600 |
| 2007-DE-17010-P | Neubaustrecke Wendlingen - Ulm | 101.450.000 | 101.450.000 | 0 |
| 2007-DE-18030-P | Neubau der Eisenbahnbrücke über die Donau bei Deggendorf | 7.010.000 | 7.010.000 | 0 |
| 2007-DE-18050-S | Variantenunabhängige Untersuchungen zum Ausbau der Donau zwischen Straubing und Vilshofen | 16.500.000 | 16.500.000 | 0 |
| 2007-DE-60490-P | Ausrüstung von Lokomotiven der Railion Deutschland AG | 4.800.000 | 3.200.000 | 1.600.000 |
| 2007-DK-20060-S | Studies for the capacity improvements of the section between Copenhagen and Ringsted | 10.990.000 | 10.990.000 | 0 |
| 2007-DK-20070-S | Studies for upgrading the railway access lines to the future Fehmarn Belt fixed link - from Ringsted to Rødby and the intersection in Kastrup | 11.700.000 | 11.700.000 | 0 |
| 2007-EE-27010-S | Studies for a European gauge line for Rail Baltica (Estonian section) | 1.000.000 | 1.000.000 | 0 |
| 2007-EE-27020-P | Cross-border section Tartu - Valga railway reconstruction/upgrading | 10.750.000 | 10.750.000 | 0 |
| 2007-EL-07020-S | Studies for the upgrading of sections on the Vertical Axis Thessaloniki - Serres - Promachonas | 2.350.000 | 2.350.000 | 0 |
| 2007-EL-07040-S | Studies for the development of the Motorway-project of PP7 (Igoumenitsa/Patras-Athens-Sofia-Budapest Motorway Axis) | 1.125.000 | 1.125.000 | 0 |
| 2007-ES-03070-P | CONEXIÓN ESPAÑA - FRANCIA POR LA FACHADA ATLÁNTICA. LÍNEA DE ALTA VELOCIDAD MADRID - PAIS VASCO - FRONTERA FRANCESA. TRAMOS VALLADOLID - BURGOS - VITORIA. OBRAS DE PLATAFORMA VALLADOLID - BURGOS | 24.999.972 | 24.999.972 | 0 |
| 2007-ES-03140-S | ESTUDIOS PARA LA CONSTRUCCION DE LA LÍNEA DE ALTA VELOCIDAD MADRID - PAIS VASCO - FRONTERA FRANCESA. TRAMOS VALLADOLID - BURGOS - VITORIA. | 14.650.000 | 14.650.000 | 0 |
| 2007-ES-03150-P | LÍNEA DE ALTA VELOCIDAD MADRID ¿ PAIS VASCO ¿ FRONTERA FRANCESA. OBRAS DE PLATAFORMA DE LOS TRAMOS ARRAZUA/MONDRAGON | 26.759.986 | 26.759.986 | 0 |
| 2007-ES-19060-P | Obras en la Conexión ferroviaria Corredor Mediterráneo ¿ Línea de alta velocidad Madrid-Barcelona-Frontera Francesa | 22.860.000 | 22.860.000 | 0 |
| 2007-EU-03080-P | Studies and Works for the High-Speed Railway Axis of South-West Europe (PP3) - Lisbon-Madrid Axis: Cross-Border Section Evora-Merida | 312.660.000 | 312.660.000 | 0 |
| 2007-EU-03110-P | Works for construction of a high-speed railway section between Perpignan and Figueres | 69.750.000 | 69.750.000 | 0 |
| 2007-EU-60040-P | EEIG ERTMS Users Group ¿ testing activities | 6.000.000 | 6.000.000 | 0 |
| 2007-EU-60120-P | ERTMS Implementation on the Railway Corridor D (Valencia - Budapest) | 21.040.000 | 21.040.000 | 0 |
| 2007-EU-60410-S | Programme Management Office (PMO) for the ERTMS deployment on the corridor from Rotterdam to Genoa | 1.130.000 | 1.130.000 | 0 |
| 2007-EU-60440-P | Mise en place de l'ERTMS sur les rames THALYS | 4.800.000 | 4.800.000 | 0 |
| 2007-FI-12010-P | Rail connection from Kouvola to Kotka/Hamina ports, works for improving and costruction of a new railway yard | 6.600.000 | 6.600.000 | 0 |
| 2007-FI-12040-P | Main railway connection to Russian border , works for development of railway section between Lahti and Vainikkala | 23.150.000 | 23.150.000 | 0 |
| 2007-FR-03130-S | Etudes préliminaires et d'APS en vue de la construction d'une nouvelle ligne ferroviaire entre Bordeaux et la Frontière Espagnole | 17.100.000 | 17.100.000 | 0 |
| 2007-FR-17210-P | Ligne à grande vitesse (LGV) Est Européenne - Seconde phase, section Baudrecourt- Vendenheim (Etudes et travaux préparatoires) | 18.000.000 | 18.000.000 | 0 |
| 2007-FR-24070-P | Ligne à grande vitesse (LGV) Rhin - Rhône Branche Est | 198.000.000 | 198.000.000 | 0 |
| 2007-HU-06100-S | Studies for preparation of approval of the railway line section Budapest - Keleti - Miskolc - Nyiregyhaza | 8.000.000 | 8.000.000 | 0 |
| 2007-HU-18090-S | Studies for Improvement of the navigability on the Danube (Hungarian section of the Priority Project No. 18) | 4.000.000 | 4.000.000 | 0 |
| 2007-HU-22020-S | Preparation of design for approval for the railway line section Biatorbagy (incl.) - Tata (excl.) of PRIORITY AXIS NO. 22 | 1.250.000 | 1.250.000 | 0 |
| 2007-IE-26010-S | Dublin Interconnector Tunnel Study- Design and Railway Order Phase | 10.000.000 | 10.000.000 | 0 |
| 2007-IT-06020-S | Tratta Ronchi sud - Trieste: Progetto Prioritario 6 - sezione Nazionale | 24.000.000 | 24.000.000 | 0 |
| 2007-IT-24010-S | Railway node of Genova - Study for upgrading the section Genova Voltri-Genova Brignole | 5.050.000 | 5.050.000 | 0 |
| 2007-IT-60030-P | Migration towards ERTMS/ETCS for Trenitalia on-board equipment | 7.000.000 | 7.000.000 | 0 |
| 2007-LV-27050-S | Studies for a European gauge line (Latvian section) | 1.100.000 | 1.100.000 | 0 |
| 2007-NL-05020-P | Works for replacement of legacy systems by 15/25 kVAC on two remaining sections in the Netherlands of the railway corridor Rotterdam Genoa. | 19.880.000 | 19.880.000 | 0 |
| 2007-NL-18010-P | Maasroute, Upgrade of Inland Waterways from class Va to class Vb specifications | 81.780.000 | 74.749.858 | 7.030.142 |
| 2007-NL-60060-P | ERTMS implementation on the railway corridor Rotterdam Genoa - Netherlands Part - Kijfhoek and Zevenaar | 4.650.000 | 4.650.000 | 0 |
| 2007-NL-60160-P | Serial fitment of onboard ETCS equipment SRS 2.3.0 in 109 freight locomotives. | 9.050.000 | 7.750.000 | 1.300.000 |
| 2007-NL-60310-P | ERTMS implementation the Railway Corridor Rotterdam Genoa Netherlands part - Section Port Railway of Rotterdam | 4.500.000 | 4.500.000 | 0 |
| 2007-NL-60380-P | Retrofit of 90 Siemens ES64F4 E-locomotives with Alstom ETCS L2 equipment for usage on EU freight corridors and various conventional networks | 9.000.000 | 9.000.000 | 0 |
| 2007-SE-12090-P | Works for construction of the road section Norra Länken | 56.150.000 | 56.150.000 | 0 |
| 2007-SE-12100-P | Works for construction of Malmoe - Citytunnel project | 51.830.000 | 51.830.000 | 0 |
3) Conditional extension 2014-2015 | 2007-AT-17040-P | Works and Studies for upgrading the Wien-Bratislava railway line (6 sub-projects) | 129.850.000 | 129.850.000 | 0 |
| 2007-BE-18040-P | Etudes de construction d¿une écluse de 225mX25m (classe VIb) à Huy (Ampsin-Neuville) et construction d¿une écluse de 225mX25m (classe VIb) à Flémalle (Ivoz-Ramet), toutes deux sur la Meuse | 17.590.000 | 17.590.000 | 0 |
| 2007-BE-18070-P | Construction of a 225 x 25 m chamber navigation lock, its ancillary works and a pumping station/ hydroelectric power plant on the Albert Canal, to the east of the existing lock complex at Lanaye. | 26.930.000 | 26.930.000 | 0 |
| 2007-DE-04020-P | Ausbaustrecke 23 (Grenze D/F) Saarbrücken - Ludwigshafen (POS Nord) | 10.000.000 | 10.000.000 | 0 |
| 2007-DE-17020-P | Ausbau des Abschnittes Freilassing-Grenze D/A (Salzburg) des TEN-Korridors Paris - München - Bratislava | 8.544.272 | 8.544.272 | 0 |
| 2007-DE-17200-P | Aus- und Neubaustrecke Stuttgart-Wendlingen einschl. Stuttgart 21 | 114.470.000 | 114.470.000 | 0 |
| 2007-DE-20010-S | Eisenbahn-Hinterlandanbindung zur Fehmarnbeltquerung von Lübeck nach Puttgarden | 12.700.000 | 12.700.000 | 0 |
| 2007-DE-24030-S | Studien für den Bau der Neubaustrecke Rhein/Main-Rhein/Neckar | 35.450.000 | 22.988.760 | 12.461.240 |
| 2007-DE-24040-P | Duisburg - Emmerich | 63.330.000 | 63.330.000 | 0 |
| 2007-DE-24060-P | Ausbaustrecke / Neubaustrecke Karlsruhe - Basel mit teilweisen Ausbaumaßnahmen an der bestehenden Strecke | 94.500.000 | 94.500.000 | 0 |
| 2007-DE-60320-P | Ausrüstung der Eisenbahnstrecke von Emmerich (Grenze) bis Basel (Grenze) mit ETCS als Teil des Korridors A Rotterdam - Genua | 23.250.000 | 23.250.000 | 0 |
| 2007-EL-29010-S | Railway line between Antirrio and Ioannina, studies for designing of the new line Antirrio-Ioannina | 21.500.000 | 21.500.000 | 0 |
| 2007-EL-29030-S | Studies for standardisation and upgrading design for the existing Patras - Pyrgos - Kalamata railway | 15.500.000 | 15.500.000 | 0 |
| 2007-ES-03050-P | Construcción de la Nueva Red Ferroviaria en el Pais Vasco ( Y Vasca) - Tramo Guipuzcoano | 7.119.000 | 7.119.000 | 0 |
| 2007-EU-01180-P | PRIORITY PROJECT TEN NO. 1 BRENNER BASE TUNNEL - WORKS | 592.650.000 | 592.650.000 | 0 |
| 2007-EU-01190-S | PRIORITY PROJECT TEN NO. 1 BRENNER BASE TUNNEL - STUDIES | 193.350.000 | 193.350.000 | 0 |
| 2007-EU-06010-P | Nouvelle liaison ferroviaire Lyon-Turin Partie commune franco-italienne de la section internationale | 671.800.000 | 662.620.000 | 9.180.000 |
| 2007-EU-06030-S | Crossborder Railway Line Trieste/Divaca : study and design of the Trieste-Divaca-Ljubljana-Budapest-Ukrainian Border | 50.700.000 | 50.700.000 | 0 |
| 2007-EU-16010-S | Studies for the construction of the new high capacity line through the Pyreneans | 5.000.000 | 5.000.000 | 0 |
| 2007-EU-19010-P | Studies and Works in the High -Speed Rail Interoperability in Iberian Peninsula (PP19) - Oporto-Vigo Axis:Cross-Border Section Ponte de Lima-Vigo | 244.140.000 | 244.140.000 | 0 |
| 2007-EU-20050-P | Studies and Works for the construction of Fehmarn Belt Fixed Rail-Road link | 338.900.000 | 265.720.000 | 73.180.000 |
| 2007-EU-22070-S | Studies for the development of the Railway Priority Project No. 22 | 6.500.000 | 6.500.000 | 0 |
| 2007-EU-60400-P | Deployment of ERTMS on the corridor Antwerp-Basel/Lyon | 88.980.000 | 88.980.000 | 0 |
| 2007-FI-12050-P | Works for the development of the railway connection between Helsinki airport and the PP12 lines | 17.760.000 | 17.760.000 | 0 |
| 2007-FR-03120-P | Désaturation du noeud ferroviaire de Bordeaux | 21.277.000 | 21.277.000 | 0 |
| 2007-IT-60360-P | Trackside ERTMS equipment on Italian part of Corridor A (600 km) | 33.000.000 | 33.000.000 | 0 |
| 2007-LT-27030-P | 1)Building of new European gauge line on the cross-border section PL border - Marijampole 2) cross-border section Siauliai - LV border. Reconstruction/Upgrading | 72.800.000 | 45.703.339 | 27.096.661 |
| 2007-LT-27040-S | Studies for Rail Baltica, Lithuanian part: a)section PL border - Marijampole in European Gauge; b) Improvement of existing line; c)contribution to global Rail Baltica study for European Gauge | 16.070.000 | 16.070.000 | 0 |
| 2007-PT-03030-P | Studies and Works in the High-Speed Railway Axis of South-West Europe (PP3) - Lisbon-Madrid Axis: Third Tagus Crossing (TTC) | 51.310.000 | 51.310.000 | 0 |
4) Conditional extension & partial cancellation (post 2015) | 2007-AT-18020-P | Implementation of the Integrated River Engineering Project Danube East of Vienna km 1921.0 - 1872.7 | 36.389.769 | 22.420.501 | 13.969.268 |
| 2007-BE-02030-P | Diabolo - Raccordement ferroviaire de l'aéroport de Zaventem au réseau à grande vitesse Thalys | 15.000.000 | 14.920.689 | 79.311 |
| 2007-BE-28050-P | EuroCap-Rail modernisation de l'axe ferroviaire Bruxelles-Luxembourg | 30.180.000 | 21.331.958 | 8.848.042 |
| 2007-DE-17220-P | Ausbaustrecke 23 Kehl - Appenweier (POS Süd) | 26.950.000 | 23.426.931 | 3.523.069 |
| 2007-EU-03040-P | Atlantic branch of the international section of PP3 Vitoria-Dax ( estudios y obras para la nueva linea de alta velocidad) | 70.000.000 | 56.808.784 | 13.191.216 |
| 2007-EU-30010-P | The Seine-Scheldt Inland Waterway Network - Cross-border section between Compiègne and Ghent | 420.190.000 | 375.928.794 | 44.261.206 |
| 2007-FR-03010-P | Contournement de Nîmes et Montpellier (Etudes et travaux) | 56.260.000 | 47.571.056 | 8.688.944 |
| 2007-IT-01030-M | Southern Access line to Brenner | 58.810.000 | 45.920.000 | 12.890.000 |
| 2007-LU-28020-P | EuroCap-Rail. Modernisation de l'axe 3 Bruxelles-Luxembourg-Strasbourg | 27.000.000 | 3.517.839 | 23.482.161 |
| 2007-LV-27060-P | 1)Reconstruction/upgrading: cross-border section north Valmeira - Valka abd cross-border section south Jelgava - LT border. 2) Reconstruction/upgrading Jugla (Riga city border station) - Valmiera | 22.330.000 | 6.541.950 | 15.788.050 |
| 2007-UK-13010-P | Package for improvements and upgrade of road infrastructure on Priority Project 13: Sections of A14, M6 and A1 | 80.710.000 | 77.665.741 | 3.044.259 |
Grand Total |
|
| 5.300.799.999 | 4.989.309.349 | 311.490.650 |